From the Archives: “This Day in History”

From the Archives:  “This Day in History”

Kingsley Dam was completed in 1941, so as we approach in 2016 the 75th anniversary of the dam and the beginning of project operations, we will be posting a list of historical highlights from the District’s past, sort of a “This Day in History” compilation. The entries will added according to when they occurred over the calendar year.

APRIL

April 11, 1941 — George Johnson, Central’s chief engineer and general manager, predicted that the Platte River would have a steady year-round flow within three years.  The construction of Kingsley Dam and Lake McConaughy, which would store flows in the North Platte River for irrigation deliveries and hydroelectric generation, would eliminate the “no-flow” periods — particularly in the central Platte stretch — that were common before the dam was built.  (Subsequent history would prove Johnson largely correct.)  The canal system — including the Supply Canal and the irrigation canals — would eventually contribute underground return flows helped stabilize base flows in the river.

NOVEMBER

Nov. 1, 1933 – The Central Nebraska Public Power and Irrigation District was officially organized after State Engineer Roy Cochran gave conditional approval to a reorganization of the District. The District’s creation had initially been approved by the Nebraska Department of Roads and Irrigation on July 24, 1933 as the Central Nebraska Public Power and Irrigation District, although several hurdles remained to be cleared. Having made progress toward gaining approval and funding for the hydro-irrigation project, the new organization – officially called THE Central Nebraska Public Power and Irrigation District – was created by the state engineer’s approval on Nov. 1.

Nov. 7, 1940 – Central’s board of directors signed a farm management contract with the University of Nebraska, placing what was called the Tri-County Farm Management Farm (which was used to demonstrate best management practices to farmers still learning about irrigated farming) under the supervision of the University’s Board of Regents.

November, 1940 — The two dredges pumping fill for Kingsley Dam — one upstream and one below the dam — completed the project that built (at the time, behind Ft. Peck Dam on the Missouri River in Montana) the second largest hydraulic-fill dam in the world.  Approximately 25.5 million cubic yards of sand and gravel were pumped during the process.  Following completion of dredging activities, workers plugged the huge tube that carries water from the North Platte River beneath the dam (now connected to the Morning Glory Spillway) and water began passing through the Control Tower.  The process of filling the reservoir was expected to begin in the spring of 1941.

November, 1965 – Central crews, under the supervision of Kingsley Dam Division Manager Bernard Donelan, finished what was originally planned to be a three-year project of placing 800-lbs. tetrahedrons on the face of Kingsley Dam. The 16,360 “tets” were placed in a matter of months because the growing season proved to be wet, resulting in low demand for water from Lake McConaughy and freeing up members of the crew to work on the dam instead of their normal irrigation-related duties. A private contractor poured the concrete jackstones at a site near the dam and subsequently manufactured several thousand more to stockpile near the dam. The jackstones were designed to protect the dam’s face by breaking wave action against the dam.

November 2004 – Maps prepared from data accumulated by the UNL Conservation and Survey Division revealed, “Significant and persistent declines in some areas of the state (that) have only become more obvious in the last few years due mainly to current drought conditions and resulting increases in groundwater pumping.” The UNL Water Center noted a spike in well drilling that occurred after passage in the spring of LB962 (a law intended to prevent conflicts between groundwater and surface water users) that spurred a rush to drill additional wells before a moratorium on new wells in some areas went into effect. According to UNL hydrogeologist Jim Goeke, “The increase in pumping and diminished recharge to the aquifer due to drought disrupts groundwater flow to streams, delaying or diminishing the flow of surface water in many basins.”

November 2009 – After 25 years and generation of almost 2 million megawatt-hours of electricity, the Kingsley Hydroplant finally required significant repairs and maintenance. Central crews began complete disassembly of the turbine-generator unit prior to repair of bushings in the turbine hub, cavitation repair on the turbine blades, refurbishment of wicket gates and oil seal improvements. The $4 million project was completed by March 2010.

OCTOBER

Oct. 10, 1955 – Central’s board of directors and management announced plans to build a 100-megwatt power plant to be fueled by natural gas. The plant, which went on-line in 1958, was constructed adjacent to the Supply Canal southeast of Lexington, was named the Canaday Steam Plant after Ralph O. Canaday, who served as the District’s legal counsel during the formative years of efforts to bring an irrigation project to south-central Nebraska and later served as Central’s chief legal counsel and general manager.

Oct. 17, 1956 – During a drought in the mid-1950s, Lake McConaughy dropped to its lowest elevation on record since the reservoir’s initial fill. The lake’s elevation on this date was 3,198.2, with a volume of 348,900 acre-feet. At the time, the reservoir’s maximum capacity exceeded 1.9 million acre-feet, so the amount of water behind Kingsley Dam represented only 18.4 percent of capacity. The low-water mark would stand until September 2004 when the lake fell to an elevation of 3,197.6 feet during another extended drought. At that time, Lake McConaughy contained 341,400 acre-feet, or 19.6 percent of its current maximum capacity of 1,743,000 acre-feet. The reservoir’s maximum capacity was lowered in the early 1970s after a 1972 windstorm damaged the protective face of the dam.

Oct. 19, 1964 – A project began to replace an original – and somewhat iconic – structure along Central’s Supply Canal. The “High Bridge,” located on a county road over the canal south of Cozad was 219 feet long and stood 74 feet above the canal’s water surface was originally constructed in 1938 and was the highest bridge in the District. Age and wear-and-tear took its toll on the wooden bridge and it was replaced by a new bridge that stands 33 feet above the canal.

bridge-construction

The original “high bridge” under construction over the Supply Canal south of Cozad.

high_bridge_replacement

The replacement bridge under construction in 1964.

Oct. 26, 1990 – More than 800 people attended a “scoping hearing” at the Ogallala City Auditorium conducted by the Federal Energy Regulatory Commission in connection with the relicensing of Central’s (and the Nebraska Public Power District’s) hydroelectric project. More than 35 people testified during the five-hour meeting, almost all in favor of issuance of a new license with conditions that would not hinder provision of the many benefits from the project.

Oct. 27, 1997 – Central construction crews began an earthwork project to raise the head above a siphon on the E-65 Canal and to install more than 2,000 feet of synthetic membrane. The earthwork would provide six more feet of elevation above the siphon to increase the volume of water passing through the mile-long pipe. The membrane lining significantly reduces conveyance losses and prevents bank erosion along the E-65 Canal between the head gate near the Johnson Lake inlet and the siphon.

October 2001 – Central started a major rehabilitation project on its three Supply Canal hydropower plants. The project involved replacing the original turbines, rewinding all five generators and installing a new transformer in the J-2 hydroplant switchyard.

Construction Underway on Pedestrian Bridge over Hike/Bike Trail

Construction Underway on Pedestrian Bridge over Hike/Bike Trail

A Central crew began construction of the pedestrian bridge over the Johnson Lake outlet canal in early October. The last pilings were driven on Oct. 12, setting the stage for construction of the supporting infrastructure and deck.

When completed, the bridge adjacent to the existing road bridge will afford safe crossing of the outlet by users of the lake’s hike/bike trail. The 10-feet-wide bridge will be constructed of wood and rest on steel pilings.

Central used a 30-ton crane equipped with a pile-driver that was positioned on the existing road bridge. Using the existing bridge as a “base” for construction will save on the cost of the bridge. The bridge is scheduled to be completed before Thanksgiving.

Central personnel finish driving the last steel piling for the pedestrian bridge.

Central personnel finish driving the last steel piling for the pedestrian bridge.

The Supply Canal: Scenic Canoe Trips Await

The Supply Canal: Scenic Canoe Trips Await

Can you identify the locations of these photos?

Supply_Canal_Photo_1(a)Supply_Canal_Photo_3a

SUPPLY_CANAL_PHOTO_5a

No, they weren’t taken along a wild and scenic river, or at some national park. These photos were taken along Central’s Supply Canal, which runs from just east of North Platte to east of Lexington. Many sections of the canal wind through high banks, and narrow canyons.

The public is permitted to use the entire length of the canal for recreational purposes, excluding areas around Central’s three hydroelectric plants and NPPD’s Canaday Steam Plant. Portages around check structures are relatively easy, but getting around the hydroplants requires a lengthier overland trek. Launching a canoe or kayak may be difficult in some spots because of the shoreline protection materials (in most cases, broken concrete riprap). Many sections of the canal are paralleled by maintenance roads or state and county roads. The flow in the canal is relatively constant year-round, the water is 15 to 20 feet deep in most places, and the current is not rapid (no whitewater stretches), although caution should be exercised when approaching check gates.

The 75-mile-long Supply Canal and its many canyon lakes are used for hunting, hiking, canoeing and kayaking, camping and fishing. Only wakeless boating is allowed on the canal to prevent bank erosion.

Also, when planning a canoe or kayak trip, it’s a good idea to remember these helpful hints from the Nebraska Game and Parks Commission:

  • Wear your life jacket.
  • Take a spare paddle.
  • Don’t canoe alone.
  • Have tether ropes on both ends of the canoe.
  • Take insect repellant.
  • Take ample water.
  • Take sunscreen, sunglasses, and wide-brim hat. The sun’s reflection off the water can be intense. If it is hot, start early or later in the day and make the trip shorter.
  • Put extra clothing, gear, and food in water-proof bags.
  • Take rain gear, but not ponchos.
  • Take first aid kit. Learn what poison ivy and poison oak look like, as well as black widow and brown recluse spiders.
  • Avoid contact with livestock and wild animals.
  • Protect your feet with tightfitting wading shoes.
  • Camp only in designated areas. Obtain permission prior to camping on, or entering the water from, private land.
  • Read maps and plan ahead. Be off the water before dark.
  • TRASH: If you create it, e.g., cans, bottles, food wrappers, etc., pack it out. Don’t discard it in the water.
  • Build fires only in fire rings; drown flames and coals after use. If no fire ring exists, use only camp stoves.
  • Use caution when loading and unloading near highway or county bridges.
  • And remember, Nebraska’s weather can be unpredictable and prone to extremes of temperature, humidity, wind and rate of change. Summer storms rapidly form, are fast-moving and can have rain, hail, high winds, lightning, and tornados combined.  Pay attention to signs of bad weather, get off the water and take cover as quickly as possible if a storm is approaching.

Central Hosts Water for Food Institute Researchers

Central Hosts Water for Food Institute Researchers

A group from the Robert B. Daugherty Water for Food Institute (DWFI) visited sites within Central’s irrigation service area on Aug. 18 as part of a workshop aimed at “Understanding the Water-Energy-Food Nexus for Irrigated Agriculture.”

After a catered lunch at Central’s headquarters in Holdrege, the group stopped at a subsurface drip irrigation site near Loomis. The SDI system was installed several years ago as a demonstration project to investigate the use of water delivered from Central’s canal system through buried drip tape on an 8-acre pivot corner. Over the years, crop yields from the acres irrigated by the SDI system have regularly matched or exceeded yields obtained from acres irrigated under the adjacent pivot, while the volume of water has been significantly less than applied by the pivot.

The next stop was at a soybean field where the producer installed a drop-span pivot to enable irrigation of approximately 23 acres that could not be covered by a normal pivot because of obstructions. The system can use either surface water from Central’s canal, or groundwater from a well, although the well has been used sparingly recently. The pivot uses GPS control to automatically stop at the desired point to allow the producer to either disconnect or connect (depending upon which way the pivot is traveling) the drop spans to continue its path through the field.

Central Valley Irrigation representatives from Holdrege, including owner Monte Vonasek and employees Project Manager Jeremiah Johnson and Coordinator Design Manager David Hoferer, were on hand to fully explain the design challenges that had to be overcome to make the system perform the way the producer envisioned. The process of manually connecting or disconnecting the spans can be accomplished in about 15 minutes. By all accounts, the pivot has exceeded expectations and solved what was formerly a perplexing irrigation problem.

The group also visited another pivot-irrigated field – also with the capability of using either canal water or well water – near Johnson Lake. Central Valley Irrigation also provided the equipment and ingenuity to irrigate acres that previously were beyond the reach of a normal pivot. The answer in this instance was a double swing-arm pivot that bends in and out to cover hard-to-reach areas of the field.

Next, the group stopped at one of the sites along the E67 Canal system that has been equipped with telemetry equipment. Equipment was installed this spring to enable collection of data that will facilitate precision irrigation management to conserve water.

UHF radios, digitized flowmeters, rain gauges and solar panels have been installed at 26 sites (approximately 42 more turnouts will be equipped over the next two years). Real-time or near real-time data from those sites, along with data compiled at two automated weather stations in the E67 area, will be available to producers online to use with field evapotranspiration (ET) and water balances data to optimize water management and irrigation efficiency. Field data and graphs can be accessed on any device with an internet connection.

Partners in the E67 telemetry project include Central, McCrometer, the Nebraska Environmental Trust Fund, and University of Nebraska Cooperative Extension.

The group concluded the tour by visiting Central’s nearby Johnson No. 1 Hydroplant just below Johnson Lake. For many tour participants, it was the first opportunity to visit a hydroelectric facility, which was generating at nearly full capacity during the visit.

Participants from DWFI included: Nicholas Brozovic, director of policy; Isidro Campos Rodriguez, post-doctoral research associate; Timothy Foster, post-doctoral research associate; Rachel Herpel, research and outreach coordinator; Jasmine Mausbach, DWFI intern; Christopher Neale, director of research; Paul Noel, program associate; Patricia Song, DWFI intern; and Richael Young, program associate.

Other workshop attendees who were on the tour included: Rosemary Carroll, assistant research professor in hydrologic sciences at the Desert Research Institute in Reno, Nev.; Yusuke Kuwayama, Resources for the Future fellow, Washington, DC; Taro Mieno, assistant professor at the University of Nebraska-Lincoln; Mani Rouhi Rad, Ph.D. student at the University of Illinois at Urbana-Champaign; and Cameron Speir, an economist with the National Oceanic and Atmospheric Administration’s Southwest Fisheries Science Center in Santa Cruz, Calif.

Central extends special thanks to the gentlemen from Central Valley Irrigation for sharing their time and expertise; to Rachel Herpel for bringing the group to south-central Nebraska; to McCrometer’s Paul Tipling for helping to explain the telemetry project; and to producers Scott Ford, John Ford, and Willie Knoerzer (a member of Central’s board of directors) for taking the time to explain their innovative pivot operations to the group.

The DWFI group at J-1 Hydroplant.

The DWFI group at J-1 Hydroplant.

From the Archives: Electronic Equipment Will Monitor Supply Canal

From the Archives: Electronic Equipment Will Monitor Supply Canal

The following article, republished from the August, 1964 edition of The Central Nebraska Irrigator, Central’s newsletter, tells about a rudimentary alarm system along Central’s Supply Canal, which was the precursor of today’s Supervisory Control and Data Acquisition (SCADA) system that monitors and controls water conveyance and hydroelectric generation throughout Central’s hydro-irrigation project.

The article was, in a way, clairvoyant. The writer may or may not have had some foreknowledge of what was to happen in the near future, but it also demonstrated that even in 1964, Central was ahead of its time.

Eight years after the article was written, the Gothenburg Control Center went into operation (in January, 1972) when remote supervisory control was established over the Diversion Dam, the Supply Canal’s hydroplants and control structures and the head gates of the irrigation canals. All are now monitored on computers at the Control Center by a supervisory control operator.

Control of Kingsley Hydro, NPPD’s Keystone Dam and the head gates of NPPD’s supply canal at the east end of Lake Ogallala were later added to the Control Center’s responsibilities because of the need for close coordination between the three components of the system to ensure proper flows into the canal and down river.

Communication is the key to such an automated system. The District has its own microwave system, supplemented by buried cable and VHF radio links. All information gathered at the remote terminal units (RTUs) is fed into the Control Center’s computers.

There are more than 1,800 alarm, control or telemetering points on the system which monitor and/or control functions of canal structures, pump stations, the three Supply Canal hydros and Kingsley Hydro.

The Control Center computer is programmed to receive data from the RTUs, check for alarm conditions and alert the operator to any abnormal readings. The operator’s control console includes a video screen that shows the current condition at any selected location on the system. Control functions are accomplished on a keyboard. The control room is manned around the clock every day of the year.

The automation enables Central to: 1) increase the generation of hydropower; 2) better manage the system under high-water conditions, i.e., sudden, heavy rain storms; 3) reduce the incidence of spills; 4) reduce maintenance needs on the canals as a result of better control of flows; and 5) reduce operating costs.

 From The Central Nebraska Irrigator, July/August, 1964

Electronic Equipment Will Provide Constant Check of Central’s 75-Mile Long Supply Canal

Gothenburg Division personnel in charge of operating Central’s 75.6-mile-long Supply Canal are sleeping a little better these days as an alarm system has been installed that will automatically notify the operator on duty at Jeffrey Hydroplant of a high- or low-water situation at any of four locations along the canal.

(Editor’s note:  The featured image on the blog page shows the transmission equipment located adjacent to water level detection equipment on the Supply Canal.)

Designed by Central’s Assistant Chief Engineer Ed Hamilton, the equipment was installed by the District’s electrical crew and members of the Gothenburg Division. The alarm systems have been installed at mile posts 5.1, 11.9, 31.2 and 35.9. These locations were considered as strategic or the most critical along the lengthy canal route.

Dale Craig, Jeffrey Plant operator, checks receiver equipment linked by radio to transmission equipment along the Supply Canal.

Dale Craig, Jeffrey Plant operator, checks receiver equipment linked by radio to transmission equipment along the Supply Canal.

A water control gate is located at each of the four points and the alarms will tell the Jeffrey operator if water is high or low behind the gate or high or low below the gate.

The Jeffrey operator will also receive a visual and audio alarm should the power fail at any of the four locations.

The alarm equipment at the four canal sites includes electrodes and relays that are located in corrugated metal pipe wells upstream and downstream from the structure gates. These detect the high or low water levels. This equipment is connected to a radio transmitter with a tone encoder and timer that are mounted with a battery and battery charger as a power source.

When a high or low water level, or power failure occurs, the tone code is transmitted to the Jeffrey Power House by the radio transmitter and this code then switches on the proper light on a small panel at the power operator’s desk that indicates the location and type of trouble. A horn sounds at the same time.

The plant operator, hearing the horn, then checks the panel and determines by the light the location and type of trouble. He then silences the horn and contacts a canal patrolman or supervisor by phone and reports the trouble.

The four installations are the initial ones for the Supply Canal and it is expected that eight more locations will be included in the future.

A third phase in Central’s efforts to gain tight control of the Supply Canal will be automatic water recording equipment located at several points along the canal.

This equipment, by tone transmissions over the District’s Supply Canal telephone line, will give hourly readings of the canal water levels and gate openings.

The hydro plant operators will also be able to question this equipment at any time between the hourly readings.

When installed, the plant operator, after receiving a signal of high or low water conditions at any point on the canal, could then question the water recording equipment and find out exactly how high or low the water is. By questioning the water recorder at short intervals he could then determine if the trouble was of a temporary, self-correcting nature or if it is necessary to report the condition to a canal patrolman or his supervisor.

The information supplied by the alarm and recording equipment will give the Central District 24-hour coverage of its Supply Canal with instantaneous indications of canal trouble such as flooding from heavy rains, leaks or malfunctioning gates.

As the District gains more experience in the installation and operation of such electronic equipment, it is anticipated that similar systems will be worked into the hundreds of miles of irrigation canals owned and operated by the District.

Central donates floating pumps to Johnson Lake area fire departments

Central donates floating pumps to Johnson Lake area fire departments

The Central Nebraska Public Power and Irrigation District donated four portable water pumps this summer to fire departments in the Johnson Lake area.

The floating pumps will enable the volunteer fire departments – from Lexington, Elwood, Cozad and Eustis – to access water directly from lakes or canals in the vicinity of fires to supplement water available from tanker trucks.

The four pumps cost a total of about $13,000 and, according to Central Public Relations Advisor Tim Anderson, are kind of like insurance.

“We hope they never have to be used,” he said, “but they’ll be a nice addition to the fire fighters’ equipment in the event of a fire at the lake or another remote area where access to water is limited.”

The donation of the pumps came in the wake of a multiple-structure fire at Johnson Lake in 2013. One cabin was completely destroyed and two other cabins sustained extensive damage.

Anderson said the after-action report indicated that responding fire departments encountered difficulties with obtaining enough water to fight the fires.

He added that the pumps can be deployed quickly and, given the mutual aid agreement between the four fire departments, all four pumps could be used at the same time if necessary. Each pump can deliver about 300 gallons per minute.

“We thought – and the board of directors agreed — it was a good use of the lake improvement fund,” Anderson said, referring to money budgeted each year for improvements at Johnson Lake.

NRCS Boss, Employees Tour Project

NRCS Boss, Employees Tour Project

Employees of the U.S. Department of Agriculture’s Natural Resources Conservation Service (NRCS) toured Central’s hydro-irrigation project on July 14. Tour participants included Nebraska NRCS State Conservationist Craig Derickson of Lincoln and representatives from NRCS offices in Grand Island, Spencer, York, Lexington, Elwood and Minden.

Participants in the NRCS tour, including State Conservationist Craig Derickson (at left) listen to an explanation of how data from an automated weather station is used in the E67 irrigation management/telemetry project.

Participants in the NRCS tour, including State Conservationist Craig Derickson (at left) listen to an explanation of how data from an automated weather station is used in the E67 irrigation management/telemetry project.

The participants assembled at Central’s office in Holdrege, then headed to several sites within the District’s irrigated area, including stops showing pivot and sub-surface drip irrigation installations on Central’s system, and automated check gate structures along the main canals. One of the highlights in the morning was a stop at a site within the E-67 Canal area where Central’s Conservation Director Marcia Trompke explained the workings of the new telemetry project.

The telemetry project began this spring with the installation of radios, remote terminal units (mini-computers that relay data), and weather stations to serve one-third of the turnouts on the E-67 system. Over the next two years, the remaining turnouts will be similarly equipped.

This project’s objective is to gather irrigation water use and environmental data to support Central’s irrigation water management, water conservation and water quality goals. The project involves the cooperation of Central’s customers irrigating about 5,800 acres in the E67 area north of Elwood and Smithfield.

The project will collect irrigation water use data from irrigation flow meters and weather monitoring sensors crucial to irrigation management. Data will be available in real time to Central and individual irrigators through digital applications to help customers make sound irrigation management decisions.

The project is partially funded by a grant from the Nebraska Environmental Trust Fund and includes partnerships with UNL Extension for educational services and the McCrometer Co., which is providing flow meters, technical expertise and equipment installation training.

The tour continued on to the Gothenburg Control Center where Electrical Superintendent Devin Brundage explained Central’s highly automated system for monitoring and controlling water all the way through its hydro-irrigation project.

After lunch at Gothenburg’s Nebraska Barn & Grill restaurant, courtesy of Central, the group then headed to the Lake McConaughy Water Interpretive Center where the participants viewed a video about the construction of Kingsley Dam and then toured the reservoir’s control structures. Kingsley Dam Foreman Nate Nielsen then explained the workings of the Kingsley Hydroplant, which was generating 30 megawatts of clean, renewable hydroelectric power at the time.

According to Nate Garrett, P.E., NRCS area engineer in Grand Island, who arranged the tour, “It was an opportunity for us to see one of Nebraska’s premier ag-engineering accomplishments and to network with one of our irrigation partners in the central part of the state. It was a fantastic tour.”

Tessa Combs, an NRCS intern who hails from Kentucky and who is working in Grand Island this summer, said, “It was really helpful to actually see the facilities and how they operate, instead of just reading about it or trying to figure out the complexities of the project by looking at a map.”

Central routinely offers tours of its hydro-irrigation project to organizations and groups throughout Nebraska, as well as groups from other states and foreign countries. If your group is interested in a one- or two-day tour of the sprawling project, contact Public Relations Coordinator Jeff Buettner at (308) 995-8601. We’ll set a date for you!

Central Conducts Exercise of Emergency Action Plan

Central Conducts Exercise of Emergency Action Plan

We’ve all heard the phrase that starts out, “In the unlikely event of … (insert here your favorite disaster).”

When it comes to a failure of Kingsley Dam, one can probably CAPITALIZE, boldface and underline the “unlikely” part of the phrase, but nevertheless, The Central Nebraska Public Power and Irrigation District is prepared. It HAS to be. Kingsley Dam impounds the largest body of water in Nebraska and its failure would be catastrophic by any measure, but if the dam failed when Lake McConaughy was full, the resulting flood would affect the Platte River Valley all the way to the Missouri River.

To be clear, the chance of a dam failure is at the lower end of the “slim to none” scale, but because of the volume of water involved and the potential consequences downstream, nothing is left to chance.

In Gothenburg Division Manager Kevin Boyd’s words, “Kingsley Dam is safe, it’s big, it’s sturdy and there are a lot of redundancies built into our ability to evacuate water rapidly to avoid overtopping or breaching the dam. Plus, there are a lot of eyes on the dam; it is constantly monitored and frequently inspected.”

But Central is prepared for the “what if’s.” As Nebraskans in many of the state’s river basins have seen all too frequently in recent years, floods caused by excessive snowmelt runoff, precipitation events or a combination of factors are a fact of life.

As part of that preparation, Central conducts a functional exercise of its Emergency Action Plan (EAP) for Kingsley Dam every five years. The object of the exercise is to coordinate with each local, county, state and federal agency on responses to such an emergency. In addition to refreshing each agency’s familiarity with their response plans, it also provides an opportunity for the agencies to provide input about how the response plans might be improved or updated.

Kingsley Dam functional exercise 6-10-15 -7 (2)

Central civil engineer Tyler Thulin, acting as a facilitator for the EAP, delivers a message to a member of the Nebraska State Patrol who was participating in the functional exercise.

During Central’s recent functional exercise, representatives from about 13 different agencies first went through a “table top” exercise where each agency outlined their planned responses in the event of an emergency. The scenario was then set for the functional exercise, which involved extremely high inflows into an already full reservoir, capped by several successive days of strong winds pushing high waves onto the dam. To provide a little realism, Central enlisted the assistance of KNOP-TV in North Platte to produce short videos containing simulated emergency broadcasts using their own on-camera reporters relaying details about the dam failure. The “broadcasts” were shown to the participants to set the stage for the functional exercise.

Participants were then dispersed throughout Central’s office in Gothenburg and the functional exercise was initiated, with messages among and between agencies flowing back and forth across the office phone system. “Facilitators” (Central employees) also helped the flow of information and communication by relaying “emergency messages” that required a response by a particular agency. For example, a message from a member of the public was given to the Nebraska State Patrol that reported a trapped motorist on a flooded road below the dam. The patrolmen on site then had to decide how they would respond given the limited ability to travel below the dam and the constraints upon available manpower.

The functional exercise simulates a dam failure or high-flow event in a stress-induced environment subject to time constraints on responses. It’s as close to reality as can be without actually mobilizing manpower and equipment. The exercise’s objectives include a determination of assets available from the various agencies, a test of how closely anticipated responses match reality, analysis of how the EAP can be improved, and providing an opportunity to improve cooperation among agencies.

In a high-inflow scenario that raises Lake McConaughy’s level to or near capacity, Central would follow an escalating set of conditions, starting with a “non-failure emergency” condition. If the situation is not resolved, Central would then enact the part of the EAP that alerts agencies about a “potentially hazardous situation developing.”

“One of the best options to save the dam that Central has is to increase releases through the “Morning Glory” spillway,” said Scott Airato, a senior civil engineer responsible for dam safety at the Federal Energy Regulatory Commission’s Chicago Regional Office. “Of course, if that becomes necessary to save the dam, the result will be significant flooding downstream.”

The next step – one that is hopefully never needed – would be implementation of responses to a dam breach or failure.

The FERC requires Central to consider every potential angle that might contribute to an event, from a sudden “sunny day” failure that starts with little flow in the river below the dam to a failure that occurs when there are already high flows in the Platte River downstream.

Removal of Lost Creek Flume

Removal of Lost Creek Flume
image (6)

Central employees begin removal of flume structure following the end of irrigation deliveries for 2014.

Work began this week on removal of the Lost Creek Flume west of Axtell. The flume, approximately 1,300 feet in length, is original to the project and has required numerous repairs. Over the years, it has deteriorated to a point that repair is no longer feasible, and Central’s board of directors voted in May to replace it with 2,700 feet of 42 inch pipeline, which will be used to continue to provide water to 1,785 acres downstream of the flume.

DSCF3389

A view from on top of the flume. Water is seen flowing through to provide irrigation water during summer 2014.

IMG_3535

The check gate shown here is used to control flow of water through the flume.

DSCF3390 IMG_3585

Summer Internship

Summer Internship

The following post was written by Kyle Gaston, one of two CNPPID summer interns working at Lake McConaughy this summer. Kyle is an environmental science major at Doane College.

0 NCM_0169
Photos by Kyle Gaston

This summer has been quite the learning experience for me having never done work with birds before. I have learned a lot and had some good and some not so good experiences this summer. Locating birds, nests, and chicks took some time but the more I worked the easier it got. The job also got more enjoyable once I gained the confidence to do it. This job wasn’t all enjoyable though just like any other job. My first day working in one of the tern enclosures, I learn quickly to not look up because those terns seem to have extremely good aim and will leave your shirt, hat, and anything else you are wearing with white stains.

On a better note, there are some fun and enjoyable parts as well. The people I work with are almost always in good humor. We always seem to be making jokes and never allow people to forget some embarrassing events such as being stuck on the beach, even though we all have been stuck at some point. Overall, working for Central has been a fun and great experience for me even if those terns leave stains all over my clothes, and I would be happy to return and work again next summer.

Snapchat-20140712080743
Photo by Kyle Gaston


1 2 3
Facebook
Twitter
LinkedIn
Instagram